Plant opening

 
Through the opening management systems you can define the opening hours of daily plant for the correct definition of the report. The change takes place as for the other registries by clicking on the yellow pencil, confirming the changes with the green check mark or reversing with the red x (Fig. 1).
fig. 1 - Managing openings
Days off calendar

With the closing calendar management capabilities, you can enter public holidays / non-working days in order to obtain a correct reporting which exclude non-working days (fig. 2).
 
 
Through the list of days of closure for insert the desired days :
  • click on new - will set a record with the current day
  • change the newly inserted record by clicking on the yellow pencil
  • select the desired date from the calendar picker and enter a description
  • confirm the selection with the green check mark or cancel it with the red x
To enter a range of dates
  • click on "Show insert stop period" on the page
  • insert the two dates by clicking on the text box to display the selector pop-up calendar
  • enter a description
  • confirm the entry by clicking on "Insert stops for selected period"